Project Case Study

 

Contract

Convert existing baby change room into a certified Changing Places facility

Intu Chapelfield Shopping Centre
40-46 St Stephens St
Norwich
NR1 3SH

Contract Value

£46,000.00

Carried Out

2018

Description

To strip out existing baby change room and install a new adult Changing Places facility that conforms to the current regulations.

Due to working in a busy shopping centre, a strict working working plan was required to ensure our workforce did not intervene with the day-to-day running of the centre. Works were carried out in allocated time slots throughout a 24 hour period to adhere to Intu's working noise policy.

Structural enhancements were required to the centre's superstructure to allow walls to be removed. Re-enforcing joists were installed above ceiling level to strengthen the slender internal block work walls.

Time management was a crucial part of this project to ensure all the different trades started and finished as per the programme, so the opening ceremony date could go ahead as planned.

The project was delivered on time and under budget, with  a high degree of satisfaction from the contract administrator as well as the client.